- thermal process areas audited
- 3
- of the electrical system baselined
- 100%
The challenge
A vertically integrated towel mill uses energy at every stage, from weaving through dyeing, drying and finishing. Heat dominates: steam for the dye house and hot air for the dryers. Without a breakdown by process, the mill could not tell which stage offered the best return on an efficiency investment.
Our approach
Our team audited the three thermal process areas, dyeing, drying and finishing, alongside a complete electrical baseline of the site. Each process was assessed for how much heat it used, how much it lost and how much could be recovered.
The result
The mill received a process-by-process picture of its energy use and a set of recommended efficiency measures, completed in July 2024.
Why it matters
In a towel mill, most of the energy is heat, and most of the heat is used in the dye house and the dryers. An audit that stops at the electricity bill misses the larger part of the cost. Breaking consumption down by process shows where recovery or better control will pay back fastest.
Running a textile mill?
A detailed audit shows where your energy goes, process by process.