- installed solar capacity
- 68 MW
- review and site QA
- 5 months
- grid handover coordinated
- PGCB
The challenge
A 68 MW solar plant is built from thousands of repeated parts: strings, combiner boxes, inverters, transformers and kilometres of cable. A small design or workmanship error repeated across the site becomes a large loss of output or a safety risk, and the grid operator will not accept power until the plant meets its requirements.
Our approach
Our engineers reviewed the plant's electrical design and approved the PV system design before construction. On site, the work covered inspection of the installation against the approved drawings, quality-assurance checks, safety-compliance checks, and coordination of the handover of power to the Power Grid Company of Bangladesh (PGCB).
The result
The plant's electrical design was reviewed and approved, and inspections continued through construction to grid handover between May and September 2024.
Why independent review matters
The owner of a solar plant depends on it producing for 25 years. An independent review of the design, and inspection during construction, catch errors while they are still cheap to correct: undersized cables, poor terminations, earthing that does not meet the grid code. It also gives the grid operator confidence at handover.
Our role
- Review of the electrical design and approval of the PV system design
- Site inspection against the approved drawings
- Quality-assurance and safety-compliance checks during construction
- Coordination of power handover with the grid operator